ModulesActivities Report

Activities Report

Every activity on a project with its quantities and cost, by day.

Where it is and who can use it

Reports › Field reporting › Activities.

Anyone who can view the activity workbench on the project can open it.

PersonActivities they get
SupervisorActivities on their own diaries and prestarts, and on the ones they are an associated supervisor on.
EngineerEvery activity on the project while Export whole project is on (the default). With it off: activities of their assigned supervisors, or every activity when none are assigned.
AdminEvery activity on the project.

The table, the CSV and the Excel file always hold the same activities for the same person and filters.

Filters

FilterWhat it does
Start dateFirst day to include.
Finish dateLast day to include. Up to 732 days after the start date.
SupervisorsOnly these supervisors’ activities. Empty means all supervisors.
StatusOnly activities on diaries with these statuses. All ticked means no limit.

An activity’s day is its diary’s date. An activity on a prestart with no diary (the prestart was never published, or its diary was deleted) uses the prestart’s day in the project’s time zone.

Choosing particular statuses leaves out activities that have no diary.

Export Excel

Export Excel starts the report with the filters on screen.

  • It appears under Excel exports below the table.
  • You get an email when it is ready. If nothing matches, the email says “No activities found.”
  • Each export has Download when it is ready, Run Again when it failed or expired, and Delete.
  • Files are kept for 90 days.

The Excel file

The file is named after the project and the dates, for example Riverside Road Upgrade Activities Report 22 June 2026 - 28 June 2026.xlsx.

Dates in the file are DD/MM/YYYY.

Activities Detail

One row per activity, in the order they were entered.

ColumnWhat it is
ProjectThe project.
SupervisorThe diary’s supervisor, or the prestart’s for an activity with no diary.
Diary DateThe activity’s day.
Cost CodeThe activity’s cost code.
Cost Code DescriptionThe cost code’s description.
Sub CodeThe activity’s sub code.
Program CodeThe activity’s program code.
Activity DescriptionWhat was done.
Target QtyThe planned quantity.
Actual QtyThe quantity done.
Qty Variance (A-T)Actual Qty minus Target Qty.
Target Qty UnitThe quantity’s unit.
Target Cost RateThe planned cost per unit.
Target Cost Rate UnitThe cost rate’s unit.
Actual CostEvery docket cost booked to the activity on this project. 0 when none.
Cost Rate VarianceActual Cost ÷ Actual Qty, minus Target Cost Rate. Blank when Actual Qty is 0 or blank, or Target Cost Rate is blank.
Activity Lacroo IDThe activity’s ID in Lacroo.

Actual Cost counts labour and plant shared across activities by hours, materials, crews, and lines allocated to the activity. It is the same figure as the Activity Workbench.

Summary sheets

SheetOne row perColumns
Summary by SupervisorSupervisorActivity Count, Total Target Qty, Total Actual Qty, Total Qty Variance, Total Actual Cost
Summary by Cost CodeCost codeDescription, then the same totals
Summary by DateDay, oldest firstThe same totals

Export CSV

Export CSV downloads the rows in the table, with the table’s columns and one column per activity custom field. It is off when nothing matched.

How the Excel differs from the table and CSV

Only the columns and their order. The activities are the same.